TRANSMISSION LINE ROUTE SURVEY
1.
The Federal government of
Ethiopia has allocated budget to
wards the cost of the Universal Electricity Access program for
increasing people’s access to electricity in rural towns and
villages.
2.
The Ethiopian Eclectic Power Corporation (EEPCo) now invites
all interested and eligible bidders for the following contracts:-
Lot-1 230 KV Transmission line survey
Route: Melkawakena-Ramo-Gode
Region: Oromia and Somali
3.
Bidding will be conducted through the National Competitive
Bidding (NCB) procedures of the purchaser’s country.
4.
Interested eligible bidders may obtain further information
from and inspect the viding documents at the office of:
Ethiopian Electric Power Corporation
Procurement Division
Head Office, De Gaulle Square
Fax 251-11-155 08 22
P.O. Box 1233
Addis Ababa
Ethiopia
5. The
bid document shall be available from April 27, 2007 on wards against
payment of non-refundable fee of ETH. Birr 500.00 for the Lot.
6. All
bids must be accompanied by a bid security of 2% of the bid price,
and must be delivered to the address above at or before 11:30 Hours
local time on may 29, 2007
7. Bids
will be opened on May 29, 2007, 15:00 Hours local time in the
presence of the bidders or their representatives who choose to
attend at EEPCO Club, Mexico Square, Addis Ababa, Ethiopia.
8. The
Ethiopia Electric power Corporation reserves the right to reject all
or part of this bids.
ETHIOPIAN ELECTRIC POWER CORPORATION |